Can you start emergency repairs before signing a contract?

Short answer. Only the emergency itself. You can act at once to stop further damage, such as shutting off the water, but the repair work needs a written contract once the situation is stabilized.

Work it through

You're the contractor. Pick what you'd do, then see how each choice plays out.

Margaret Torres

Elderly widow who needs roof repairs

A pipe burst in Margaret Torres' basement during a cold snap. Water is flooding in. She calls you in a panic at 10 PM.

"Please, can you come now? Water is everywhere!"

Emergency work — no time for a written contract before you start.

  1. Correct

    Emergency stabilization (shutting off water, preventing further damage) is reasonable to start without a contract. But once the emergency is stabilized, you must have a written contract before performing repair work. The emergency doesn't waive Maryland's contract requirements — it just justifies reasonable immediate action. Document the emergency, take photos, and get the contract signed the next morning.

  2. Wrong

    Performing thousands of dollars in non-emergency repair work without a written contract, especially for an elderly homeowner, violates Maryland home improvement law. Stopping the water = emergency. Replacing drywall and flooring = non-emergency work requiring a contract. Sending an after-the-fact bill for undefined work to an elderly widow is exactly the kind of complaint that makes headlines.

  3. Partially true

    Specialized plumbing work requires a master plumber's license. However, shutting off the water main to stop flooding is basic emergency response anyone can do. You could also help coordinate the emergency, call a plumber on her behalf, and handle the restoration work (drywall, flooring) under your MHIC license. Leaving an elderly widow alone with a flooding basement at 10 PM is not a good look.

All 19 home improvement contracts questions

  1. Is a handshake deal legal for home improvement work in Maryland?
  2. What must a Maryland home improvement contract include?
  3. Which MHIC notice must every home improvement contract include?
  4. What if a signed contract is missing the completion date?
  5. Can a Maryland home improvement contract require arbitration?
  6. What happens in a scope dispute when nothing is in writing?
  7. Does a small cash side job need a written contract?
  8. Does a $2,000 job need a written home improvement contract?
  9. Can you start emergency repairs before signing a contract?
  10. Should you give a homeowner a ballpark or a written estimate?
  11. How do you fix a vague scope of work before it becomes a dispute?
  12. How should you respond when a client redlines your contract?
  13. How should a contract handle upgrades during the project?
  14. How do you price a contract for work that starts months later?
  15. Should a multi-year renovation be one contract or several?
  16. Can you sign a home improvement contract with a 17-year-old?
  17. What happens when a homeowner fires you partway through a job?
  18. Can you substitute materials named in the contract?
  19. How should you handle materials the homeowner supplies?