What is the MHIC Guaranty Fund?
Short answer. A fund financed by mandatory contributions from every licensed contractor, under COMAR 09.08.01.20, that reimburses homeowners for actual financial loss caused by a licensed contractor's violation of home improvement law, up to set limits.
- COMAR 09.08.01.20
- COMAR 09.08.01.26
Work it through
You're the contractor. Pick what you'd do, then see how each choice plays out.
A new client asks you about the MHIC Guaranty Fund. "My friend got ripped off by her contractor and she got money back from some fund. What is that exactly?"
- Correct
The MHIC Guaranty Fund is funded by mandatory contributions from all licensed contractors (COMAR 09.08.01.20). It provides reimbursement to homeowners who suffer actual financial loss due to a licensed contractor's violation of home improvement law. The fund has a per-claim and aggregate limit. Knowing this and explaining it confidently shows professionalism.
- Dismissive
The Guaranty Fund is directly relevant to your client. It's a selling point for hiring licensed contractors — homeowners have financial protection if something goes wrong. Under COMAR 09.08.01.26, your contract must include a notice about the Guaranty Fund. Dismissing it suggests you either don't understand it or don't want the client thinking about recourse.
All 15 complaints, warranties & the guaranty fund questions
- What is the MHIC Guaranty Fund?
- What happens if you ignore an MHIC complaint letter?
- Can a homeowner file an MHIC complaint after your warranty ends?
- Is a two-day delay grounds for an MHIC complaint?
- How should you prepare for an MHIC disciplinary hearing?
- What counts as project abandonment?
- How do you respond to an MHIC abandonment complaint?
- What documentation defends you against an MHIC complaint?
- How should you handle a warranty callback?
- Does your warranty cover damage the homeowner caused?
- What do you owe a client in an after-hours warranty emergency?
- How do you run a final walkthrough and punch list?
- What should a project completion package include?
- How do you handle a client disappointed with finished work?
- Who is liable when a flip buyer finds unpermitted work?