Does added work need a written change order?

Short answer. Yes. Any change to scope, price, or timeline should be a written change order signed by both parties. It protects you from price disputes and the homeowner from unauthorized charges.

  • Business Regulation §8-501

Work it through

You're the contractor. Pick what you'd do, then see how each choice plays out.

Sarah Mitchell

First-time homeowner who wants a kitchen renovation

Midway through Sarah's kitchen renovation, she wants to upgrade from laminate to granite countertops and add undercabinet lighting. That's an additional $4,200 in materials and labor.

"Just add it to the total. We don't need to redo the whole contract, do we?"

  1. Correct

    Any change to the original contract scope, price, or timeline should be documented in a written change order signed by both parties. This protects you from 'I never agreed to that price' disputes and protects the homeowner from unauthorized charges. While Maryland law doesn't specify the exact format, the contract requirements in §8-501 apply to modifications as well.

  2. Risky

    Verbal change orders are the #1 source of contractor-homeowner disputes. When the final invoice is $4,200 higher than the contract price, Sarah may dispute it. Without written documentation, you have no proof she authorized the upgrade. This is how Guaranty Fund claims happen.

  3. Bad business

    Change orders are a normal part of construction. Refusing to accommodate them is rigid and unprofessional. The correct approach is to document the change, adjust the price and timeline, and get written approval. Many contractors make significant profit on change orders — properly managed, they're an opportunity, not a problem.

All 11 deposits, payments & change orders questions

  1. How large a deposit can a Maryland contractor take?
  2. Can you accept full payment up front for a home improvement job?
  3. Must you refund a deposit if the homeowner cancels before work starts?
  4. How do you collect an overdue progress payment?
  5. Can a homeowner hold back part of the final payment?
  6. Who pays the fee when a homeowner pays by credit card?
  7. Does added work need a written change order?
  8. Can you collect for extra work that was never put in writing?
  9. How do you handle a weather delay past the contract completion date?
  10. What if the insurance payout is lower than your estimate?
  11. How do you handle a client whose vision is bigger than the budget?